Action

 Date

Application for top car park / Information Centre

November 2010

Application to retain temporary sea wall on Crinnis

November 2010

Hybrid planning application to Cornwall Council

March 2011

Decision on hybrid planning application

Late spring/early summer 2011

Phased discharge of conditions

Summer 2011 onwards

Start sea defences

Late 2011 (target)

Commence building apartments

Spring 2012 (target)

 